Procurement takes a purchase from the first request on site to a paid supplier bill: a purchase request checked against the project budget, approvals, supplier quotes, a purchase order, goods received on site, the stock that lands in your warehouse and is then used, and a bill matched against the order and the receipt. This page walks through the whole flow; Project Controls covers the budget side in more depth.

Purchase requests

With a live budget check

Approvals

Steps by amount, inbox and reminders

Supplier quotes

Compare, then create the order

Purchase orders

Committed against the budget

Goods receipts

Receive what arrives on site

Three-way match

Order, receipt and bill agree

The procurement cycle

  1. 1Purchase
    request
  2. 2Approval
  3. 3Supplier
    quotes
  4. 4Purchase
    order
  5. 5Goods
    receipt
  6. 6In stock
    (warehouse)
  7. 7Used
    (stock out)
  8. 8Bill &
    payment

Procure-to-use cycleWhen stock runs low or the site needs more, a new request starts the cycle again.

Every step is optional except the purchase order: with no approval rules a request is approved straight away, with no quote requirement you can select a single quote, and you can always create a purchase order directly. Steps 6 to 8 don't wait for each other: in the default stock mode the goods are in stock as soon as the order is saved, you can use them before the bill arrives, and the bill is matched against the order and the receipt, not against what was used.

Where to find it

Procurement needs the POS module in your plan; the Project System › Procurement menu needs both the Projects and POS modules. The menu shows the screens you have permission for.

ScreenWhere
Purchase Requests (and their supplier quotes)Project System › Procurement › Purchase Requests
Goods ReceiptsProject System › Procurement › Goods Receipts
Purchase OrdersProject System › Procurement › Purchase Orders (the same list as POS System › Purchase)
Approval Inbox, Approval RulesApprovals › Approval Inbox / Approval Rules
Everything bought for one projectOpen a project › Procurement button

Before you start

  1. Add your suppliers as vendors (Accounting System › Vendor) and the products you buy (Products System › Product & Services).
  2. For project purchasing, set up the project's budget lines so requests can be checked against them — see Project Controls › Budget lines.
  3. Add approval rules if purchases need sign-off, and decide how many supplier quotes are required.
  4. Choose the stock posting mode in Company Settings.
  5. Give people the right permissions, or use the ready-made roles.

1. Raise a purchase request

Open Project System › Procurement › Purchase Requests and click + (Create Purchase Request), or click Request materials on the project procurement page.

  1. Choose the Project, and optionally the Project Task and Needed By date. The project is already filled in when you came from Request materials, or when you are a member of exactly one project in progress.
  2. Add items: a product or a description, Quantity, Est. Unit Price and the Budget Line it should be charged to.
  3. Watch the Budget Check panel: it updates as you type and shows, per budget line, what is left after this request.
  4. Click Save Draft to keep working on it, or Save & Submit to send it for approval.

Budget check

ResultWhat happens on submit
Within budgetThe request goes to the normal purchase request approval.
Warning: budget almost usedSame, and the approver sees the warning.
Budget exceeded: needs budget override approvalA Budget Override approval starts next to the normal one. If no budget override rule covers the request total (not the overrun), the request can't be submitted.

Items without a budget line never block. More detail: Project Controls › What the budget check does.

Request status

DraftPendingApprovedOrdered
  • Without a matching approval rule the request is Approved as soon as it is submitted.
  • A rejection makes it Rejected; edit it and submit again.
  • Only draft or rejected requests can be edited, and only drafts deleted. Cancel Request works until the request is ordered.
  • With create purchase request you see only your own requests; manage purchase request sees all of them.

2. Get it approved

Approval rules

Open Approvals › Approval Rules and click Add Step. Procurement uses three groups: Purchase Request, Purchase Order and Budget Override.

FieldMeaning
Minimum / Maximum AmountThe amount band the rule applies to. Leave the maximum empty for no upper limit.
StepSteps are approved in order: 1, then 2, …
Approver Role / Approver UserAnyone with the role, or a named user (left empty, the list shows Any role / Any user). The approver also needs the module's approve permission, and the person who raised the document is excluded. One rule counts per step: the one with the higher minimum.
Supplier Quotes RequiredPurchase requests only: how many quotes are needed before the purchase order can be created.

Approvers also need the matching permission (approve purchase request, approve purchase order, approve budget override); the company account can always approve. The person who raised a document can't approve it; only the company account can approve its own. Purchase Order rules apply to orders created directly — see POS › Purchase order approval.

Approval inbox

Approvals › Approval Inbox shows Waiting for my approval (with a red count in the menu) and My recent decisions. Approve with an optional comment, or Reject with a required comment. The requester and the next approver are notified, and a daily reminder goes out when a step has waited more than 24 hours. You can also approve from the mobile app.

3. Compare supplier quotes

Open an Approved request and click Supplier Quotes.

  1. Add Quote for each supplier: Vendor, Quoted Total, Delivery (days), Payment Terms and an optional Quote File.
  2. Compare Quotes shows them side by side with the difference from the estimate; the Lowest and Fastest are marked.
  3. When you have the number of quotes your rules require, click Select on the one you choose. In the Select Quote & Create Purchase Order window, click Create Purchase Order.

4. Create the purchase order

After selecting a quote, choose the purchase date, the category and, when your plan includes warehouses, the warehouse the goods go to. The order takes its lines from the request, and the quoted total is spread over the lines in proportion to their estimated amounts. The request becomes Ordered, and the order's amount is committed against the budget lines. You can edit the order afterwards.

To create an order without a request, open Project System › Procurement › Purchase Orders (or POS System › Purchase) and click +. Set Project and Project Task at the top and Cost Code / Budget Line on each line to charge it to a project. It may need approval before it can be sent, paid or billed.

To stop an order, use Cancel Purchase or Close Purchase; both release its budget commitment. See POS › Cancel or close a purchase order.

5. Receive the goods

  1. Open the purchase order and click Receive Goods.
  2. Choose the Receipt Date. The Warehouse appears, and is required, only when your plan has warehouses; it defaults to the order's warehouse and moves stock only in the Only when goods are received on site mode.
  3. For each line enter Received Now and, if needed, Rejected. You can't receive more than is still open; decimals are allowed. Partial deliveries are fine — receive again when the rest arrives.
  4. Click Save Receipt.

The order's Receiving & Billing panel shows ordered, received, billed and open quantities per line. Project System › Procurement › Goods Receipts lists every receipt (GRN). Deleting a receipt reverses its quantities and any stock it posted, removes its actual cost, re-opens the commitment and re-checks the order's bills. Stock can go negative, because material already used is not checked; receipts of a cancelled or closed order can't be deleted.

When stock is added

The Stock posting field in Settings › System Settings › Company Settings decides when purchased goods enter stock. For how each step uses the warehouse, and what is not available yet (transfers between warehouses, issuing to a project), see Warehouse › Procurement and Purchase Orders.

ModeStock is addedProject actual cost from
When purchase orders and bills are saved (current) — the defaultThe full ordered quantity when the order is saved. Bill lines not linked to an order line (even on a bill from an order) add stock too. Close Purchase doesn't take stock back; only Cancel or Delete doThe supplier bill
Only when goods are received on siteOnly by a goods receiptThe goods receipt
Switching the mode affects new purchase orders only. Each existing order keeps the mode it was created under. Details: Project Controls › Stock posting.

6. In stock: the warehouse

Purchased products (not services) are added to the product's total stock and, when your plan includes warehouses, to one warehouse. Which warehouse and when depends on the stock posting mode the order was created under:

ModeWarehouseQuantity added, and when
When purchase orders and bills are saved (current) — the defaultThe purchase order's warehouseThe full ordered quantity, when the order is saved, before anything arrives. The warehouse on a goods receipt moves no stock.
Only when goods are received on siteThe warehouse chosen on each goods receiptOnly the quantity received, when the receipt is saved. Rejected quantities are not added.

Where to see the stock:

  • Products System › Product Stock: each product's total quantity. The View Warehouses button on a row shows how it is split over warehouses.
  • Products System › Warehouse, then open a warehouse: the products and quantities held there.
  • Accounting System › Reports › Product Stock: every stock movement with its source (Purchase, Bill, Goods Receipt, Invoice, Pos, Manually, Debit Note) and description.
  • POS System › Reports › Warehouse Report: how products are spread over your warehouses.

There is no automatic reorder alert. The Product Stock list only marks a product Low Stock at 5 units or fewer, so check it and raise a new purchase request when you need more. More on warehouses: Warehouse & Inventory.

7. Use it: stock out

Stock goes down only in these ways:

ActionTakes stock out of
A customer invoice, when it is created (also a proposal converted to an invoice)The warehouse chosen on each invoice line. A converted proposal reduces only the product total.
A POS saleThe warehouse chosen in the POS
Subtract Stock in Products System › Product Stock › Adjust StockThe product total and, if you pick one, a warehouse. You can't subtract more than the product's total stock.
Add Debit Note on a supplier bill that has a payment (company account only), for goods returned to the supplierThe bill line's warehouse, and the returned amount comes off the project cost. Lines of a bill created from a purchase order have no warehouse on the bill and can't be returned with quantities: only an amount-only debit note is possible, which moves no stock, so take the returned goods out with Subtract Stock.
Undoing a purchase: deleting a goods receipt (receipt mode), cancelling or deleting a purchase order (default mode), deleting a bill line that added stockThe stock that document added
Not available yet: issuing material from a warehouse to a project, site or task, and linking what is used to a budget line. The system keeps quantities in the warehouse and money on the project separately. Workaround: when material leaves for a site, use Subtract Stock on the warehouse it leaves and name the project (and task) in Reason (Optional). It then shows in the Product Stock report as Manually with your note.

The material's cost reaches the project through the purchase, not through its use. The amount of each purchase order line is committed against its Budget Line when the order is saved, and becomes actual cost when the supplier bill is saved (default mode) or the goods are received (receipt mode). Subtracting stock changes no project cost, so don't also record it as a project expense, or the cost is counted twice. See Project Controls › Stock posting.

8. Bill, match and pay

On the purchase order click Create Bill from PO. The bill opens filled with the open quantities, prices, cost codes and budget lines, and stays linked to the order. Its Three-Way Match panel compares order, receipt and bill:

  • Quantity: billed must not exceed received (receipt mode) or ordered (default mode).
  • Price: the bill's unit price must be within 2% of the order price.

The bill is marked Matched or Exception (bills with no linked order lines are Not Matched). A bill marked Exception can only be paid by the company account, and while any bill of the order is Exception other users can't add a payment on the purchase order either. Paying a bill needs create payment bill, which no ready-made role has. Pay the bill as usual — see Accounting › Bills.

Project procurement page

Open a project and click Procurement to see all purchasing for that project on one page.

CardShows
Open requestsDraft, pending or approved requests not ordered yet
Committed on ordersThe gross amount of the project's purchase orders, cancelled, closed and fully received ones included. The open amount is in the card's Open: hint; Budget Control's Committed column is the open commitment.
ReceivedReceived quantity × order price
BilledBills before tax
Budget usedOpen commitment + actual cost as a % of the budget lines' revised total (or of the project budget when there are no lines)

Below the cards are the project's purchase requests, purchase orders (with % received, Receive Goods and Create Bill from PO), goods receipts and bills (with their match status). Request materials opens a new request with the project filled in.

Permissions

PermissionAllows
create purchase requestRaise and edit your own requests
manage purchase requestSee and edit all requests
approve purchase request / approve purchase order / approve budget overrideAct on approval steps of that type
manage approval rulesApproval Rules screen
manage supplier quotesAdd quotes and create the purchase order
manage goods receiptReceive goods, Goods Receipts list
manage purchasePurchase Orders list (create / edit / send purchase for the matching actions)

These are on the POS tab of the Create / Edit Role screen (Purchase Request, Supplier Quotes, Goods Receipt, purchase order approval). The migration gives approve permissions only to the company role; the ready-made roles from Create Project Controls roles already include them (see Ready-made roles). Add them to other roles in Roles & Permissions. The ready-made Site Engineer, Procurement Officer, Project Manager and Finance roles are described in Project Controls › Ready-made roles.

Quick reference

TaskPath
Raise a purchase requestProject System › Procurement › Purchase Requests › +, or Project › Procurement › Request materials
Approve or rejectApprovals › Approval Inbox
Set who approves whatApprovals › Approval Rules › Add Step
Compare quotes and create the orderPurchase request › Supplier Quotes
Create an order directlyProject System › Procurement › Purchase Orders › +
Receive goodsPurchase order › Receive Goods
See what is in stockProducts System › Product Stock, or Products System › Warehouse
Take stock out by handProducts System › Product Stock › Adjust Stock › Subtract Stock
Bill an orderPurchase order › Create Bill from PO
All purchasing for one projectProject › Procurement