Semantik ERPDocs

Projects

The Project Management module provides tools for managing projects, tasks, timesheets, milestones, and bug tracking. It helps teams deliver projects on time and within budget.

Projects Overview

Projects opens a portfolio view built for project managers: what is late, what is at risk, and where the budget and hours go.

Summary cards

Six cards sit at the top. Click any card to filter the list:

CardCounts
ActiveProjects in progress
Overdue projectsPast their end date and not complete or canceled
At risk / off trackIn-progress projects whose health is not "On track"
Over budgetSpent more than the budget
Overdue tasksOpen tasks past their due date, across all projects
Due in 30 daysProjects ending within the next 30 days

Filters and sorting

  • Search by project name, tag or client.
  • Status and Health chips, Client, Team member and Due (overdue, this week, 30 days, no end date).
  • Sort by nearest deadline (default), health, lowest progress, highest budget use, name or newest.
  • By default the list shows In progress and On hold projects. Filters stay in the address bar, so you can bookmark or share a view. Reset clears them.

What each row shows

ColumnMeaning
HealthOn track / At risk / Off track — hover to see why
ProjectName, client, status and tags
TimelineStart → end, days left or overdue, and a bar comparing time used with tasks done
ProgressWeighted task progress — see how progress is weighted
TasksOpen, done/total and overdue tasks
BudgetPercentage used and spent / budget. Spent = timesheet labour cost + project expenses
HoursLogged hours / estimated hours
TeamMembers of the project
⋮Open, Task board, Gantt chart, Timesheet, Edit, Invite user, Duplicate, Delete — as your role allows

How health is decided

Health is calculated for projects In progress; other statuses just show their status.

  • Off track — the end date has passed, spending is over budget, the project is more than 30 points behind schedule (time used % minus progress %), or SPI or CPI is in Act now.
  • At risk — there are overdue tasks, it is more than 15 points behind, 90% or more of the budget is used, it ends within 7 days at under 80% progress, or SPI or CPI is in Watch.
  • On track — none of the above.

The 15 / 30 points and the 90% / 100% budget limits are the defaults; change them in KPI Settings. SPI and CPI come from the latest earned value snapshot and are ignored until one exists. Hover the health badge to see the reasons and, when available, SPI and CPI in plain words (for example SPI 0.92: Behind schedule by 8%).

Sync team to all projects (⋮ More, next to Create Project) adds every company user to every project and creates a general task in each, so everyone can log time. It needs the edit project permission.

Project Setup

Creating a Project

  1. Navigate to Project System > Projects
  2. Click + Create Project
  3. Fill in project details
FieldDescription
Project NameDescriptive name
ClientAssociated client
Start DateProject begins
End DateExpected completion
BudgetProject budget
Estimated HoursTotal hours planned
StatusIn Progress/On Hold/Completed/Canceled

Project Status

StatusDescription
In ProgressActively being worked on
On HoldTemporarily paused
CompletedSuccessfully finished
CanceledTerminated

Adding Team Members

  1. Open the project
  2. In the Members card, click + (or use Invite User from the project's ⋮ menu)
  3. Pick the users to add

Only members can log time on a project. Long member lists scroll inside the card.

Task Management

Task Stages

Configure task workflow in Project System > Project System Setup > Project Task Stages:

  • To Do
  • In Progress
  • Review
  • Done

Creating Tasks

  1. Open project
  2. Go to Tasks tab
  3. Click + Create Task
  4. Enter: Task Name, Priority, Assigned To, Due Date, Description
  5. Optionally: WBS Code, Task Budget and Weight, used by Project Controls

Task Board (Kanban)

View tasks in Kanban format:

  • Columns represent stages
  • Drag cards between columns
  • Quick view of workload

Task Details

Each task includes:

  • Subtasks/Checklist: Break down into smaller items
  • Comments: Team discussions
  • Files: Attach documents and screenshots
  • Time Logged: Hours worked on task

Milestones

Milestones mark significant project checkpoints.

Creating a Milestone

  1. Open project
  2. In the Milestones card, click + (Create Milestone)
  3. Enter Title, Status, Start Date, Due Date and Cost (all required), and an optional Description

Milestone Progress

Milestone progress is not calculated from tasks. Set it by hand with the Progress slider when you edit the milestone. The milestone count on the project page (for example 3/5) counts milestones whose Status is Complete.

Timesheet & Time Tracking

Time Entry Methods

Method 1: One entry

  1. Go to Project System > Timesheet (or a project's Timesheet page) and click Add Timesheet / Log time
  2. Choose the task, the date and the time spent, and add a description
  3. Save

Method 2: Mobile app

Log one day or a whole range from your phone: Mobile app › Projects and timesheet.

Method 3: Fill Several Days (split between tasks)

Use this to log a whole period at once, for example a month, and share the days between one or more tasks by percentage.

  1. Go to Project System > Timesheet, choose the employee and month
  2. Click Add Multi Timesheet
  3. Pick the date range
  4. Select a task and its percentage. Click Add task for more tasks (up to 10), or Split evenly to share 100% equally
  5. Check the Estimate table: days, hours and dates each task will get
  6. Click Save

How the days are split:

  • Only days the employee attended are used. Friday and Saturday are skipped, and so are days before the joining date or after resignation
  • Percentages must add up to 100%, and each task can be chosen once
  • Days are split as whole days in date order: the first task gets the first days, the next task the following days, and so on
  • Each day is logged with that day's attendance hours, so a task's hours can differ slightly from its percentage when daily hours vary
  • If a day already has timesheet entries, they are replaced
  • Project costs are recalculated automatically after saving

Example: 20 attended days of 8 hours, split 25% / 25% / 50%:

TaskPercentageDaysHours
Task A25%5 (days 1–5)40
Task B25%5 (days 6–10)40
Task C50%10 (days 11–20)80

Project Timesheet

Open it from a project (Timesheet button) or from the ⋮ menu in the projects list. It shows who logged what, on which task, for any period.

  • Period: This week (Sunday–Saturday), Last week, This month, Last month, or a custom range of up to 5 years.
  • Filters: members and tasks.
  • Grid tab: one row per member and task; columns are days, weeks (ranges over a month) or months (ranges over about six months), with totals.
  • Summary tab: hours by member (with share, days, tasks and labour cost), by task (all-time hours against the task estimate) and by week.
  • Entries tab: every entry with edit and delete.
  • Export downloads the entries shown as an Excel file; Log time adds an entry.
People without the control timesheet permission only see their own entries. Labour cost comes from payroll, so it covers the payroll months of the chosen period.

Monthly Timesheet (Daily Log)

Project System > Timesheet shows one employee's month: required hours (from attendance), logged hours, remaining and the status of every day — Complete, In Progress or Missing.

  • A day is complete once the logged time reaches the required time.
  • Hours logged on weekends or vacation days are listed too.
  • Each entry shows its project and task; click it to edit.
  • With control timesheet you can pick any employee of your company.

Timesheet Report

Project System > Timesheet Report compares attendance with logged time for every timesheet employee over a range of payroll months: attendance hours, timesheet hours, project vs non-project hours, the difference and a coverage percentage. Export Excel downloads the same rows with net salary. It needs the project expenses permission.

Project Cost Tracking

The system tracks all costs associated with projects, including labor costs from timesheets, direct expenses, and overhead allocation.

How Timesheet Costs Work

Each timesheet entry contributes to the project's total cost:

  1. Employee logs hours to a project
  2. For each payroll month, the system spreads the employee's net pay (from the payslip) over all the time they logged in the payslip period
  3. Each project gets the share of net pay that matches its share of the logged time

Hourly Rate Calculation

Project Cost = Net Pay × (Time on the project / All time logged in the payslip period)

Example:
Employee Net Pay: 10,000
Time logged in the period: 160 hours (all on projects)
Cost per logged hour: 10,000 / 160 = 62.50

There is no fixed number of monthly hours. Net pay is spread over the time actually logged: if the employee logs only 80 hours, the whole net pay is charged across those 80 hours. Time logged outside any project sends its share of net pay to the overhead pool. If the employee logs no time in the period, the salary goes to no project and is only listed as unlogged on Projects Expenses.

Cost Distribution Example

Employee works on 3 projects in a month:

Project Alpha: 40 hours → Cost: 40 × 62.50 = 2,500
Project Beta:  80 hours → Cost: 80 × 62.50 = 5,000
Project Gamma: 40 hours → Cost: 40 × 62.50 = 2,500
─────────────────────────────────────────────────
Total:        160 hours → Cost: 10,000 (= Net Salary)

Project Expenses

Track additional costs beyond labor:

Direct Expenses

Expenses linked to specific projects:

  • Software licenses
  • Travel costs
  • Fuel, petty cash and small hires
Buy materials and subcontractor work through purchase requests, purchase orders, goods receipts and bills, not as project expenses. That way Budget Control sees the commitment, the items enter your warehouse stock (see Stock posting), and the bill is checked by three-way match. Equipment bought as a project expense is charged to the project in full, with no depreciation.

Adding an Expense

  1. Go to Project System > OverHead and click Create (or Insert Overhead on Projects Expenses)
  2. Enter Name, Date and Amount, and pick the project in Projects. If you pick several projects the amount is split equally between them
  3. Optionally choose a Cost Code
  4. To set the Budget Line or attach the receipt, open the project, click Expense and use Edit on the expense
The Create button on the project's Expense page (shown with the view expense permission) currently does not save the expense. Use OverHead instead.

Overhead Expenses

Company-wide costs not tied to specific projects (rent, utilities, admin costs): entries in OverHead with no project, plus the salary share of time logged outside any project. Each payroll month this pool is shared across the projects that have cost that month, in proportion to their direct cost:

Project Overhead = Overhead Pool × (Project Direct Cost / Direct Cost of All Projects)

Example:
Overhead Pool: 5,000
Project Alpha Direct Cost: 10,000
Direct Cost of All Projects: 50,000

Project Alpha Overhead = 5,000 × (10,000 / 50,000) = 1,000

Total Project Cost Formula

Total Project Cost = Timesheet Costs (labor)
                   + Direct Expenses
                   + Payslip Allocation
                   + Overhead Allocation

Project Income

Track revenue received from projects. Income is not entered on the project page:

  1. Go to Project System > Projects Income
  2. Click + (Create New Project Income)
  3. Enter: Projects, Amount, Notice Date, Comment

It needs the project expenses permission.

Profitability Analysis

The system does not calculate profit or margin. To compare income with cost, use Export year Total Ex on Projects Expenses: the Excel file lists each project's income (Past Income, Total Income for the year, Total Income) next to its cost and its cost with a markup (25% by default). It has no profit column, so work out profit yourself.

Timesheet-Payslip Integration

Payroll reaches project cost in two separate ways:

  • Employees with Has TimeSheet are costed automatically from their logged time (see above)
  • Employees without timesheets (for example site workers) are linked by hand in Project System > Project Payslips, one payroll month at a time. Each payslip is split equally across the projects it is attached to, not by hours. This is the on-site salary cost
  • Attaching a timesheet employee in Project Payslips has no effect on project cost

Cost Reports

ReportDescription
Cost by UserBreakdown of project costs by team member
Cost by TaskCosts allocated to each task
Yearly SummaryExport year Total Ex: monthly direct, overhead and total cost per project, cost with markup, and income. It has no profit column

Viewing Project Costs

  1. Go to Project System > Projects Expenses
  2. Select date range
  3. View breakdown by:
    • Timesheet expenses (labor)
    • Direct expenses
    • Overhead allocation
    • Total cost
  4. Export reports in Excel format

Bug Tracking

Bug Statuses

Configure in Project System > Project System Setup > Bug Status:

  1. New
  2. Open
  3. In Progress
  4. Resolved
  5. Closed
  6. Reopened

Reporting a Bug

  1. Open project
  2. Go to Bugs tab
  3. Click + Create Bug
  4. Enter: Title, Assigned To, Priority, Status, Description

Bug Details Include

  • Steps to Reproduce: Numbered list
  • Expected Result: What should happen
  • Actual Result: What happens instead
  • Screenshots: Visual evidence

Bug Workflow

NewOpenIn ProgressResolvedClosed

Won't Fix · Reopened

Reports & Analytics

Project Dashboard

Overview metrics:

  • Progress: Overall completion %
  • Hours: Logged vs estimated
  • Budget: Spent vs allocated
  • Tasks: Completed vs total

Progress Calculation

Project Progress = Σ (task progress % × task weight) ÷ Σ task weight
                   (weight = Weight, else Task Budget, else 1 per task; completed tasks count 100%)
Hours Progress = (Logged Hours / Estimated Hours) × 100
Budget Progress = (Expenses / Budget) × 100

Available Reports

ReportWhereShows
Projects overviewProjectsHealth, deadlines, budget and hours of every project
Project timesheetProject › TimesheetHours by member, task and week, with Excel export
Timesheet ReportProject System › Timesheet ReportAttendance vs logged time per employee
Project ReportProject System › Project ReportPer-project users, tasks and logged hours. The project detail page works fully only for the company account: other roles may see no project or a different one
Projects ExpensesProject System › Projects ExpensesTimesheet labour, on-site salaries, project expenses and overhead. Supplier bills and goods receipts are not included; they appear in Budget Control and Earned Value

The project page's Total project time spent and Last 7 days hours count every member's time, compared with the project estimate.

Project Controls

Budgets per cost code, purchase requests with approvals, goods receipt, change orders, baselines and earned value are described in Project Controls. On the project page:

  • Budget Control — budget lines with committed, actual and available amounts, budget revisions and change orders.
  • Earned Value — SPI, CPI, EAC, VAC and TCPI with a plain-language sentence under each, the S-curve, and the project's baselines.
  • Procurement — the project's purchase requests, purchase orders, goods receipts and bills, with Request materials to raise a new request. See Project procurement page.

Project expenses have optional Cost Code and Budget Line fields so they land on the right budget line.

Quick Reference

TaskPath
Create ProjectProjects > + Create
Add TaskProject > Tasks > + Create
Log TimeProject System > Timesheet > Add Timesheet
Fill Several DaysProject System > Timesheet > Add Multi Timesheet
Project timesheet & exportProject > Timesheet > Export
Projects at riskProjects > "At risk / off track" card
Report BugProject > Bugs > + Create
Add MilestoneProject > Milestones card > +
Add ExpenseProject System > OverHead > Create
Add IncomeProject System > Projects Income > +
View CostsProject System > Projects Expenses
View TasksProject System > Tasks
Budget linesProject > Budget Control
SPI / CPIProject > Earned Value